Winter Maintenance for BAC Cooling Towers: A Practical Cold-Weather Operating Plan

Winter operation places a cooling tower in one of its most demanding conditions. The heat load may fall, but the risk of uneven water distribution, frozen components, unstable controls, stagnant water, fan problems, and unplanned downtime rises.

For a Baltimore Aircoil Company cooling tower, the right winter strategy begins with the exact model, serial number, installed accessories, certified drawing, and operating manual. BAC offers many equipment configurations, including the crossflow Series 3000 and Series 1500, counterflow PT2, centrifugal-fan Series V, industrial Series 5000, and several closed-circuit products. Those differences affect airflow, service access, water distribution, drive systems, and cold-weather procedures.
The goal is not to apply one universal winter rule. It is to build a coordinated plan for the equipment actually installed.
Begin with the BAC Equipment Record
Before inspecting the tower, assemble the operating package:
BAC model and serial number
Product-specific operating and maintenance manual
Certified equipment drawing
Original selection and design conditions
Fan and drive information
Heater, remote-sump, and control submittals
Approved sequence of operation
BAS points and alarm list
Water-treatment program
Previous inspection and repair records
BAC maintains an online manual library organized around specific equipment models. Project teams should use that model-specific material rather than relying on instructions for a similar-looking tower.
For certain units, BAC also directs owners to contact the local representative using the model and serial-number information located near the access door.
Determine the Winter Operating Mode
The maintenance plan should identify how the tower will operate under four distinct conditions.
Continuous wet operation
Facilities with year-round cooling loads may operate the tower during freezing weather. The system needs:
Adequate flow through each active cell
Reliable water distribution
Stable leaving-water-temperature control
An approved fan-speed range
Freeze protection during low load and standby
Continuous treatment and monitoring
An operator response for visible ice
Hospitals, laboratories, higher-education facilities, industrial plants, and buildings with large interior loads commonly require this level of planning.
Intermittent wet operation
Intermittent operation can create additional risks because equipment repeatedly starts, stops, drains, refills, or remains wet between calls for cooling.
Document:
What enables the condenser-water or spray pump
Which cells and valves open
How flow is proven
When the fan is allowed to start
What happens after the pump stops
Which components drain
How idle cells are treated
How the system responds to a power failure
The CDC recommends avoiding stagnation and dead legs, recirculating water during intermittent operation, and using automated treatment controls.
Dry operation
Some BAC closed-circuit or hybrid products may support dry operation under appropriate conditions. A closed-circuit tower contains an internal process-fluid loop and an external spray-water circuit. Switching to dry operation does not remove the need to protect or properly drain the external water system.
The exact dry-operation sequence should come from the manual for the installed product. It should explain:
Whether the spray pump stops
Whether the basin drains
How coil fluid is protected
How valves are positioned
What minimum process-fluid flow is required
When wet operation resumes
Seasonal shutdown
A seasonal shutdown should cover:
Cleaning and disinfection
Basin and piping drainage
Trapped-water inspection
Makeup-water isolation
Treatment-system shutdown
Heat-trace requirements
Electrical isolation
Fan and drive preservation
Spring recommissioning
The CDC recommends cleaning and disinfecting according to manufacturer guidance before startup, after shutdown, and when the system has been idle. It also recommends an offline cleaning and disinfection at least annually.
Maintain Adequate Water Flow
Water flow is one of the most important variables in cold-weather operation. Excessive turndown can produce uneven distribution, leaving some areas dry and concentrating water in others. Localized conditions can then promote icing, reduce thermal performance, and stress fill or other components.
The winter sequence should identify:
Design flow for the tower
Minimum acceptable flow per active cell
Cell staging order
Pump-speed limits
Bypass-valve limits
Flow-proof requirements
Response to loss of flow
Treatment of isolated cells and equalizer lines
In a multicell system, operating fewer cells with adequate water loading may be preferable to spreading insufficient flow across every cell. That decision should be verified against the BAC manual and approved by the system engineer.
During inspection, check:
Strainers
Distribution basins
Spray branches
Nozzles or orifices
Balancing valves
Headers
Makeup assemblies
Evidence of uneven distribution
Debris, scale, or biological deposits
Fan operation should not be used to compensate for a water-distribution problem.
Verify Fan and VFD Operation
A VFD can provide useful capacity control, but not every speed is mechanically acceptable.
BAC’s Series 1500 instructions warn that when fan speed is changed from its factory setting, including through a variable-speed device, the system must avoid operation at or near the fan’s critical speed. BAC instructs users to consult the local representative for those applications.
For each tower, document:
Minimum and maximum approved fan speed
Any prohibited or critical-speed range
Acceleration and deceleration requirements
Fan cycling limitations
Vibration-switch setpoints
Low-temperature fan lockout
Sensor-failure fallback
Whether reverse operation is permitted
Do not assume fan reversal is an acceptable de-icing strategy. It should only be used when expressly authorized for the exact BAC model, fan, drive, and operating condition.
Inspect the complete drive system:
Fan blades and pitch
Blade clearance
Bearings
Belts and sheaves
Gear drive and lubricant
Couplings and shafts
Motor and motor space heater, if furnished
Guards
Vibration cutoff switch
Mounting hardware
Abnormal sound or vibration
BAC’s maintenance guide includes reference procedures for vibration cutoff switches, bearing maintenance, belt tension, sheave alignment, fan installation, motor orientation, pump selection, and water-quality guidance.
Understand What a Basin Heater Protects
A basin heater protects the cold-water basin against freeze-up when properly selected, installed, powered, controlled, and submerged. It should not be treated as freeze protection for the entire condenser-water system.
BAC describes its immersion basin heaters as UL- and CSA-rated devices intended to prevent cold-water-basin freeze-up. Available configurations vary in voltage, phase, capacity, and element length.
A separate evaluation is needed for:
Makeup-water piping
Equalizer piping
Overflow and drain lines
Pump connections
Exposed risers
Level-control piping
Chemical-feed tubing
Sensors and pressure taps
Idle branches
Valves outside the heated basin
Piping that does not drain completely
BAC heater controls can include a single probe that senses water temperature and level, contactors, a 24-volt control transformer, and a NEMA 4 enclosure.
Before winter, functionally test:
The heater only operates when required.
The element remains properly submerged.
The low-water cutoff prevents dry firing.
The contactor energizes correctly.
The temperature sensor responds accurately.
The heater is interlocked appropriately with pump operation.
The BAS receives the required alarm or status.
The branch circuit and disconnect are correctly identified.
A graphics-screen command is not proof that the heater is producing heat. Verify voltage, current, and control response using qualified electrical personnel and safe test procedures.
Evaluate a Remote Sump Where Appropriate
BAC remote sump tanks are typically installed indoors in conditioned space. When the pump stops, recirculating water can drain from the outdoor tower, closed-circuit cooler, or evaporative condenser into the indoor tank. BAC states that this arrangement can eliminate the need for cold-water-basin heaters and can centralize water-quality monitoring for multicell installations.
A remote sump is not automatically freeze-proof. Successful operation depends on:
Correct piping slope
Adequate pipe diameter
Open drain paths
Proper air relief
Absence of traps
Sufficient tank volume
Correct operating level
Reliable pump suction
Protection of makeup and overflow piping
Controls coordinated with drain-down
Verification after field modifications
A remote sump may be a strong long-term solution for frequently operated winter systems, but it is a design decision rather than a substitute for maintenance.
Keep the Water-Management Program Active
Winter does not eliminate microbial risk. Reduced load can increase water age, create stagnant cells, or produce inconsistent chemical control.
The CDC identifies four central Legionella risk factors in cooling towers:
Sediment and biofilm
Temperature
Water age
Disinfectant residual
The CDC recommends automated disinfectant control, avoidance of stagnation, appropriate recirculation during intermittent operation, and a formal water-management program.
OSHA also emphasizes routine inspection, cleaning, disinfection, and documentation. Recommended records include system descriptions, operating procedures, treatment use, inspection and cleaning dates, sampling results when sampling is performed, and maintenance activities.
The winter plan should define:
Responsible members of the water-management team
Treatment control limits
Monitoring frequency
Bleed and makeup operation
Conductivity control
Corrective actions
Management of idle cells
Cleaning and disinfection triggers
Sampling policy
Record retention
Response to an out-of-limit condition
ASHRAE Standard 188-2021 establishes minimum Legionella risk-management requirements for building water systems. ASHRAE Guideline 12-2023 provides additional control guidance, while Standard 514 addresses broader physical, chemical, and microbial water-system risks.
Inspect the Tower Structure and Heat-Transfer Components
Inspect for:
Scale and biological deposits
Damaged or displaced fill
Blocked airflow passages
Damaged louvers
Deteriorated drift eliminators
Corrosion
Loose fasteners
Cracked fiberglass
Coating failure
Sealant failure
Standing water
Structural deformation
Evidence of previous ice loading
The CDC recommends high-efficiency drift eliminators and advises locating cooling towers at least 25 feet from building air intakes to reduce the possibility of drift entering the ventilation system.
For an existing installation, do not relocate equipment or add screens without an engineering review. Airflow changes can affect recirculation, capacity, sound, plume behavior, and structural loading.
Manage Ice Through an Approved Procedure
Some ice may appear during freezing operation, but its location, rate of growth, and effect on the equipment determine whether the condition is manageable.
Escalate when ice:
Approaches the fan or rotating equipment
Restricts airflow
Blocks water distribution
Loads fill, louvers, eliminators, or structural components
Produces abnormal vibration
Creates falling-ice hazards
Blocks access
Grows rapidly or asymmetrically
Appears outside the conditions anticipated by BAC
Do not strike fill, louvers, eliminators, basins, coils, piping, or structural members with impact tools. Do not use an improvised fan-reversal sequence.
Apply the facility’s lockout/tagout, electrical-safety, fall-protection, chemical-handling, and PPE procedures before inspection or corrective work. OSHA notes that cooling towers can expose workers to aerosols and emphasizes proper maintenance, disinfection, and worker protection.
Functionally Test the Complete System
Before freezing weather, test:
Condenser-water or spray-pump start and stop
Proof-of-flow interlocks
Fan enable
VFD operation through the approved range
Cell isolation valves
Bypass valves
Basin heaters
Heater low-water cutoffs
Makeup-water assemblies
High- and low-level alarms
Low leaving-water-temperature alarms
Temperature sensors
Conductivity and treatment controls
Loss-of-power response
BAS alarm transmission
Standby-equipment changeover
Trend:
Outdoor-air temperature
Entering- and leaving-water temperatures
Basin water temperature
Pump speed and status
Fan speed and status
Flow, where measured
Valve positions
Heater status
Conductivity
Makeup and bleed operation
Alarm history
Trend data can expose unstable fan cycling, leaking valves, incorrect sensors, insufficient water flow, simultaneous heating and pumping, or a heater that is commanded on but not operating.
Prioritize Findings by Risk
Immediate correction
Fan contact with ice
Rapid or structurally significant ice buildup
Failed low-water cutoff
Dry-fired or damaged heater
Frozen or leaking piping
Loss of treatment control
Failed flow proof
Severe vibration
Inoperative critical alarm
Blocked drain-down path
Short-term repair
Damaged insulation
Intermittent heat trace
Poor nozzle distribution
Corroded hardware
Unreliable valve actuator
Sensor calibration error
Minor fill or eliminator displacement
Capital planning
Remote sump conversion
Controls modernization
VFD retrofit with critical-speed evaluation
Major basin or casing restoration
Chronic low-flow correction
Cell-isolation improvements
Replacement of obsolete drives or unsupported controls
Tower replacement or conversion to a different heat-rejection strategy
Pre-Winter BAC Checklist
Equipment information
BAC model and serial number recorded
Correct BAC manual available
Certified drawing available
Installed accessories documented
Approved winter sequence available
Local BAC representative identified
Mechanical systems
Fan and drive inspected
Critical-speed restrictions documented
Vibration cutoff tested
Strainers and distribution system cleaned
Fill, louvers, and eliminators inspected
Drains and overflow lines verified
Remote-sump drain-down tested, if applicable
Freeze protection
Basin heater amperage and control operation tested
Low-water cutoff tested
Heat-trace circuits tested
Pipe insulation inspected
Makeup and equalizer piping reviewed
Trapped-water locations identified
Power-failure behavior verified
Controls
Flow proof functionally tested
Fan sequence tested
Cell valves stroked
Temperature sensors calibrated
Alarm routing verified
Standby equipment tested
Trends reviewed under low-load operation
Water management
Treatment equipment operational
Control limits documented
Idle cells addressed
Conductivity control tested
Cleaning and disinfection documented
Corrective-action responsibilities assigned
Safety and response
Lockout/tagout procedure current
Fall and ice hazards evaluated
PPE available
Unsafe ice-removal methods prohibited
Emergency contacts current
Night and weekend response established
The Bottom Line
Reliable winter operation of a BAC cooling tower depends on the interaction of water flow, fan control, freeze protection, drainage, water treatment, mechanical condition, and operator response.
For an owner, the payoff is reduced outage and repair risk. For facilities staff, it is a repeatable procedure instead of an improvised response during a freeze. For engineers and contractors, it is a system whose intended operation can be tested and documented. For healthcare and education facilities, it supports both continuity and responsible water management.
The best first step is to place the exact BAC manual, certified drawing, winter sequence, control limits, inspection findings, and alarm-response plan into one asset-specific operating package. Then functionally test that package before freezing conditions expose its weaknesses.